The main part of the Husab project is the Rössing South orebody, about 5 kilometres south of the Rössing mine and 45 km northeast of Walvis Bay port. Husab plans to mine 15 million tonnes of ore per year from two separate open pits to feed a processing plant designed to produce 6000t U3O8 per year. Mine construction commenced in 2014. Production started at the end of 2016, during which year 192t U3O8 was produced. Production will ramp up to 5500t U3O8/year by 2020, with most of the product being supplied to China and up to 20% being marketed internationally by CGN Global Uranium Ltd, incorporated in the UK.